CoPA Consent to Noisy Works

CoPA gives local authorities powers in relation to noisy works on construction sites.

The Act does not remove these however it has made subtle changes to the way in which disagreements are resolved. If a dispute arises the final arbiter will be the Secretary of State rather than the courts.

Normally the Councils would have 28 days to consider a consent application but this is not long enough for complicated applications. Consequently the Councils secured an undertaking through the petitioning process that HS2 will engage early to seek agreement on provision of noise mitigation (e.g double gazing, temporary rehousing, hours of work, site screening, equipment to be used) to demonstrate that the “best practicable means” (BPM) for reducing noise from construction activities will be used. During negotiations with others, Chiltern and South Bucks proposed an innovative “statement of expectations”, which was accepted by the promoters as a mutually beneficial way of managing construction noise impacts.

Section 61 Statement of Expectations

Following this a guidance document for HS2 contractors was written, which has become the process for negotiation on the Best Practicable Means. A risk based approach has been adopted.

 


Documents



Latest Update


Meetings continue to be held with the enabling work contractors to discuss programme and risk.

Activities are mostly concerning vegetation clearance, archaeological and ground investigation work. Where future noisy works may impact residents, risk assessments have been undertaken and appropriate action has been taken.

Ground investigation works are in progress in Chiltern and South Bucks, with works commenced at the Amersham vent shaft site.

Habitat creation near the site of the proposed Chalfont St Peter vent shaft is due to commence in November 2017.

Major works to construct the M25 slip roads have also commenced. The majority of these will be within Three Rivers District Council jurisdiction, with impacts in Chiltern and South Bucks areas. Engagement with HS2 Ltd, Highways England and contractors are on-going, with contractor KIER submitting an application for consent to carry out noisy works on Shire Lane.


Meetings have been held with the enabling works contractors to discuss programme and risk. To date activities have been limited to vegetation clearance, archaeological works and ground investigations. Where future noisy works might impact residents, risk assessments have been undertaken by contractors and a 'statement of intent' submitted.

Major works to construct the M25 slip roads will commence shortly of which the majority of works will be in the Three Rivers District Council area but will affect Chiltern and South Bucks Districts as well.

Engagement with HS2, Highways England and contractors currently on-going.